Lynnwood Link enters training and testing phase this week

Wednesday, May 22, 2024

Sound Transit train testing in north Shoreline
from the pedestrian overpass
Screenshot from video by Steve Treseler
Testing on the Lynnwood Extension of the 1 Line enters a new phase this week. This phase includes training for operators and maintenance staff, and continued testing to ensure stations, tracks, utilities, and vehicles work together as expected in preparation for the start of service this summer. 

Light rail vehicles will run frequently between the Northgate and Lynnwood City Center stations.

In addition to trains on the tracks, people can expect to see maintenance vehicles, testing equipment, and personnel involved in the testing process, and hear sounds typical in an operating light rail system including station announcements, wheels on the tracks, and warning signals. 

This is an exciting new phase of the project that brings us one step closer to opening the Lynnwood Link Extension.

While this phase gets underway, we’ll keep working to finish building the new 8.5 mile extension to Lynnwood. Earlier this year, nearby residents may have noticed new activity on the tracks and at stations that have been part of Systems Integration Testing. 

Those activities have included:

Rail grinding: Rail grinding is a routine preventative maintenance activity that prolongs the lifespan of light rail tracks. Crews grind away the top layer of material from the rail. The work generally occurs when rail is installed and then repeated every 2-3 years. Nearby residents and businesses may have heard increased noise and seen localized sparks as a result of this work.

Dead car tows: Dead car tows involve crews towing a single light rail car along the tracks at walking speed to test clearances around the trains when they begin running. Nearby residents and businesses may have seen light rail vehicles on the tracks moving slowly along as crews verify clearances.

Rider information and alert systems testing: Crews need to test systems like fire alarms, track intrusion detection, rider information, and more before the system opens. Nearby residents and businesses should expect to hear these systems being tested prior to the light rail line opening for service.

Sign up for alerts to stay up-to-date on construction. Residents who will be living near an active light rail station can find out more information on what to expect for operational noise here. Learn more about the Lynnwood Link Extension here.


0 comments:

Post a Comment

We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.

ShorelineAreaNews.com
Facebook: Shoreline Area News
Twitter: @ShorelineArea
Daily Email edition (don't forget to respond to the Follow.it email)

  © Blogger template The Professional Template II by Ourblogtemplates.com 2009

Back to TOP