These work activities are for building noise and retaining walls that are necessary to keep the project on schedule. This work is a part of the Lynnwood Link Extension project.
Residents can expect construction noise from equipment being operated at night, such as a crane, forklift, manlifts, light plants and various hand tools. Work will involve noise, not much louder than freeway noise, to adjacent neighbors.
This night work will consist of five (5) weeks to complete this task. Installation of noise and retaining walls is weather dependent. If the work becomes delayed, a new flyer will be provided to residents.
Work hours will be 6pm to 4am the following morning for the dates below.
Work hours will be 6pm to 4am the following morning for the dates below.
- Week 1: Monday, Dec. 19 - Friday, Dec. 23
- Week 2: Tuesday, Dec. 27 - Friday, Dec. 30
- Week 3: Tuesday, Jan. 3 - Saturday, Jan. 7
- Week 4: Monday, Jan. 9 - Saturday, Jan.14
- Week 5: Monday, Jan. 16 - Saturday, Jan. 21