The work is performed at night to help minimize community disruption and traffic impacts. This work is part of the future Lynnwood Link Extension link light rail project.
What:
- Residents can expect construction noise from equipment being operated at night, such as Forklift, Manlifts, Crane, Light Plants, and Hand Tools.
- If the work takes longer than expected or the work is delayed, additional ramp closures will be scheduled, and new flyer will be distributed.
- Week #1
- Monday-Thursday, 8/29 – 9/1 (11:00pm – 5:00am)NE 145th St to Northbound I-5 On-Ramp closure
- Tuesday-Thursday, 8/30 – 9/1 (11:00pm – 5:00am)Northbound I-5 to NE 145th St Off-Ramp closure
- Week #2
- Tuesday-Thursday, 9/6 – 9/8 (11:00pm – 5:00am)Northbound I-5 to NE 145th St Off-Ramp closure
- NE 145th St to Northbound I-5 On-Ramp closure
- Detour routes are in place (see maps).
- Community Engagement: c-jaybee.ragudo@soundtransit.org or 206-701-1469
- After-hours construction hotline: 888-298-2395