Concrete repairs on I-5 scheduled to begin next week

Friday, January 28, 2022

File photo of concrete repair on I-5
Beginning Monday, January 31, a WSDOT contractor will replace concrete panels at various locations on I-5 between Tukwila and Shoreline that were damaged last year when extreme heat caused the pavement to expand and crack. WSDOT maintenance teams patched these areas, but those repairs were meant to be temporary.

The work requires nightly lane closures on I-5. Lanes will begin closing as early as 8pm in some areas, potentially reducing one direction of the highway to a single lane by midnight. All lanes will reopen early the next morning.

Crews will sawcut and excavate the existing damaged pavement, then pour new concrete panels. Many of the 46 concrete panels due to be replaced are located in the Shoreline area.

The best way to track closure locations and times is by using the WSDOT real-time travel map or downloading the WSDOT mobile app. This work is weather-dependent and will likely be rescheduled if there is rain in the forecast. 



0 comments:

Post a Comment

We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.

ShorelineAreaNews.com
Facebook: Shoreline Area News
Twitter: @ShorelineArea
Daily Email edition (don't forget to respond to the Follow.it email)

  © Blogger template The Professional Template II by Ourblogtemplates.com 2009

Back to TOP