Sound Transit begins work at 185th overpass
Sunday, June 28, 2020
![]() |
From Sound Transit |
By Diane Hettrick
As promised, Sound Transit began work on the 185th St vehicle overpass on I-5 Monday night.
Previously, they have already installed large metal utility poles, clear cut and dug up the Station area, slightly realigned 5th NE, and built a roundabout at 185th and 10th.
![]() |
185th overpass was closed overnight Monday Photo by Steven H. Robinson |
On Monday night, they shut down the 185th overpass entirely to do some road restriping and set up of temporary traffic signals.
![]() |
Temporary traffic signal. When one direction is open... Photo by Steven H. Robinson |
The 185th overpass is now one lane. A traffic light alternates traffic from east to west. The traffic is fairly smooth right now, because so many people are staying home. Under normal circumstances (remember 'normal'?) 185th is a major east west commuter route, but traffic is light now.
5th Ave is fully closed between 183rd and 185th.
The rail will go underneath 185th on the east side of I-5. They will be constructing a cut and cover tunnel during this phase of construction. Basically, the rail will stay level and they will cut a path for the rail straight through the slight rise in the ground. Then the tunnel will be covered.
![]() |
...the other direction is closed Photo by Steven H. Robinson |
The one-lane configuration will remain for two years while the rails and station are being built for the Lynnwood Link. Eventually 185th and 5th NE will be a four way stop. 185th and 8th will be a permanent roundabout for traffic into the North Shoreline Station, and the city of Shoreline would like to keep the roundabout at 185th and 10th.