Ronald Bog Park update
Tuesday, April 28, 2020
Photo by Steven H. Robinson |
The photos were taken within the week and show the progress and the growth that spring has brought to the park.
Rebecca McAndrew, Sound Transit Senior Environmental Planner reported:
Most of the work is finished at Ronald Bog. The contractor should be hydroseeding the lawn outside of the mitigation area this week. The ideal time to hydroseed is after March when there is no chance of frost.
Hydroseeding will take place very soon Photo by Steven H. Robinson |
The three interpretive signs to be installed are almost done. The parking lot will need to be restriped and there could be a few other minor things that need to be done before the park is reopened.
The sandbag wall will be removed Photo by Steven H. Robinson |
The sandbag wall (also called a cofferdam) isolates the work area from the rest of the pond so sediment-laden water (stirred up while the contractor disturbs soil) doesn’t enter the main pond and flow downstream on the North Branch of Thornton Creek.
The “fish window” — when in-water work may occur — for Ronald Bog is July 1 to September 30.
Since work continued after September 30, the wall had to be left over the winter and spring. The sandbags will be removed once the fish window opens again.
This is the plan being followed for the park.
Sound Transit My Nguyen reports that
Our crew is working on striping the parking lot and hydro-seeding the park which will take approximately three more weeks until it is completed. During this three weeks it will allow our team to assess if the park can be open to the public.
The re-opening event will be postponed until it is deemed safe to gather in large groups by our state governor. An email alert will be sent out to our readers featuring a date of the event so community members can come enjoy the new amenities to the park.
Article updated 4-29-2020