Excavation to begin soon for Shoreline Apartments in North City

Friday, February 23, 2018


The site of the Shoreline Apartments, at NE 175th and 15th NE, has been completely cleared and the next step is full scale excavation.

Excavation was scheduled for this week, but construction is often weather dependent, particularly in the early stages.

Structural concrete pours are planned to begin around the middle of April and are scheduled to be complete by middle/end of August.

Framing starts middle of August.

Completion middle of December 2019.




5 comments:

Anonymous,  February 23, 2018 at 11:09 AM  

Better hurry before the 185th station gets cut or postponed as an infill station.

Anonymous,  February 23, 2018 at 12:47 PM  

And the date/time/location of the "meeting" would be?

Anonymous,  February 23, 2018 at 8:26 PM  

After telling community members they would be a property tax exemption project (PTE), they are - submitted their application to the city council already.

Anonymous,  February 24, 2018 at 4:39 PM  

Put a moratorium on density! Put a moratorium on the density tax-breaks!

DKH February 24, 2018 at 7:07 PM  

Anonymous 12:45PM - the graphics were originally prepared for the developer meeting last year. Notifications go out only to property owners within 500 feet of the perimeter of the site, and possibly to the neighborhood association.

Post a Comment

We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.

ShorelineAreaNews.com
Facebook: Shoreline Area News
Twitter: @ShorelineArea
Daily Email edition (don't forget to respond to the Follow.it email)

  © Blogger template The Professional Template II by Ourblogtemplates.com 2009

Back to TOP