City Light to upgrade electrical cable in Lake Forest Park

Monday, August 15, 2016



Starting in early September 2016, Seattle City Light will be upgrading the aging electrical cable in parts of Lake Forest Park to help improve the electrical reliability in the area.

City Light’s contractor, Novinium, will test and where possible, inject underground cables with silicone to fill cracks in the cable insulation to prevent outages. If cables are not suited for injection, they will be replaced at a later time.

Affected customers have also been notified.

The contractor, Novinium will be working for a total of 13 days in the month of September. Daily work hours are scheduled from 8:30 a.m. to 4:30 p.m. Evening and weekend work is not planned.

One maintenance outage is anticipated for this work. All affected customers will be notified on the Thursday before the following week’s outage. The outage date and time will be specified on the notification.

The entire project is expected to last one month.

Traffic and parking impacts are expected in the immediate area during work hours. Flaggers will be used where needed on residential streets. Crews will be careful to try and maintain access to driveways.

For more information, customers can contact John Likes, Electrical Service Representative at (206) 615-0608 or john.likes@seattle.gov.

The construction website will have the latest updates on this project. 



0 comments:

Post a Comment

We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.

ShorelineAreaNews.com
Facebook: Shoreline Area News
Twitter: @ShorelineArea
Daily Email edition (don't forget to respond to the Follow.it email)

  © Blogger template The Professional Template II by Ourblogtemplates.com 2009

Back to TOP