NE 178th Street Sidewalk Project nears completion

Tuesday, December 15, 2015

Photo by Jerry Pickard
Work on the NE 178th Street Sidewalk Project in Lake Forest Park is heading into the home stretch.

Utility work is done and the final curbing is being installed this week. A test section of pervious surface concrete is scheduled for installation this week and asphalt roadway paving is scheduled for Saturday, December 19, 2015 (both weather permitting).

Turn from NE 178th St. to NE 180th St
Photo by Jerry Pickard

Once paved, the road will be reopened to traffic, with or without lane-control flagging, depending on adjacent work such as sidewalk and electrical installations.

New sidewalk by Eagle Scout Park
Photo by Jerry Pickard

The remainder of the concrete sidewalks will be done soon, also weather permitting. This will leave placement of the pedestrian-actuated crossing signs, landscaping, mitigation replanting, and the punch list of completion items.

Photo by Jerry Pickard
The new 21-foot culvert is performing well in the face of heavy rainstorms since the end of August 2015.



1 comments:

Unknown December 16, 2015 at 12:59 PM  

Thank God. Seems like the construction has taken forever.

Post a Comment

We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.

ShorelineAreaNews.com
Facebook: Shoreline Area News
Twitter: @ShorelineArea
Daily Email edition (don't forget to respond to the Follow.it email)

  © Blogger template The Professional Template II by Ourblogtemplates.com 2009

Back to TOP