Photos courtesy City of Shoreline |
Weekend Work
Paving work is scheduled at the northeast corner of the intersection of N 205th and Aurora (by Campbell Nelson) on Saturday, August 22 from approximately 10am to 4pm.
The westbound right lane of N 205th Street and the northbound right lane of Aurora by the intersection will be closed to do the work. Drivers can expect traffic delays and are encouraged to find alternate routes to avoid the area.
Traffic Revision
On Monday, August 24, all northbound traffic will be switched to the east side of Aurora into Edmonds for median work. Left turns will temporarily not be allowed from northbound Aurora to westbound N 205th during this phase of work.
Roadway Work
Paving of the median is scheduled for the week of August 24, weather permitting. One lane may be closed in either or both directions of Aurora during non-commute hours. Drivers are urged to follow posted speed limits, drive carefully, and use caution through the area as trucks will be entering and leaving the roadway.
Other work activities include curb and gutter work in the median, irrigation installation, topsoil and bark mulch placement, and signal work.
Transit routes leaving the Aurora Transit Center have changed during construction. Visit Community Transit for the latest details. Community Transit can be reached at 425-353-RIDE (7433).
No comments:
Post a Comment
We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.