Progress on 195th Separated Trail Project

Friday, February 20, 2015

NE 195th looking west from 5th AVE NE
Photo by Carl Dinse
Work is proceeding on the 195th Separated Trail project between 1st NE and 5th NE on NE 195h. The ditch was filled in and ground prepared all the way to the Holyrood property line (hedge).

NE 195th looking east from 1st AVE NE
Photo by Carl Dinse

The corner curbs have been installed, the ground leveled and filled with gravel. Next, work will begin on the street. This section of 195th is open only to local traffic.