Pages

Friday, February 13, 2015

Overnight closures of I-5 lanes for pavement repair project

I-5: NE 117th Street to SR 104 pavement repair #8633
Mileposts: 173.15 - 177.76

Concrete grinding work is underway on I-5 in Shoreline. This work takes place during overnight hours but may start as early as 8 or 9pm.

Grinding work is unavoidably noisy. To report noise concerns, or request earplugs, call 206-440-4DOT (4368)

  • Monday, Feb. 16 to the morning of Friday, Feb. 20 - Up to three lanes of southbound I-5 from Northeast 175th Street to Northeast 145th Street will be closed from 8pm to 5aml nightly for sign and barrier work.
  • Monday, Feb. 16, to the morning of Friday, Feb. 20 - Up to four lanes of northbound I-5 from Northeast 145th Street to Northeast 175th Street will be closed from 7pm to 5am nightly for concrete roadway grinding.
  • Wednesday, Feb. 18, to the morning of Friday, Feb. 20 - The northbound I-5 on-ramp from Northeast 145th Street will be closed from 9pm to 5am nightly for concrete roadway grinding.
Last update: 10:59 a.m., 2/13


No comments:

Post a Comment

We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.