Sidewalk improvements near Syre
Tuesday, January 13, 2015
Shoreline Public Works will begin work this month on sidewalk improvements on 12th Ave NW leading to Syre Elementary.
The City of Shoreline plans to install curb ramps and repair sidewalks. The design has been completed and a Contractor, Iron Creek Construction, selected to do the work which will begin the last half of this month.
The City will be installing curb ramps and transitional sidewalk on 12th Avenue NW at the following cross streets:
- NW 196th St
- NW 199th St
- NW 199th Pl
- NW 201st St
- NW 202nd St
- NW 203rd St
Following that, the City will be replacing sidewalk panels along the west side of 12th Ave NW at selected locations.
The map identifies the limits of the roadway work and those locations where the City will be replacing existing curb ramps and sidewalk.
The curb ramp/sidewalk improvements will involve travel lane and parking lane closures on 12th Avenue NW and is expected to create some traffic impacts during the day. With construction occurring along the sidewalk, pedestrian access will be impacted. The City will work with the Contractor to provide as much access as possible during construction. Work is expected to last approximately two months, into March of this year.
Contact John Vicente with any questions regarding the improvements, 206-801-2474. Additional information about the program is available on the City's webpage.
2 comments:
Meanwhile in Richmond Beach, you take your life in your hands every time you walk from the little store to the Saltwater Park. Why are we waiting for sidewalks on 20th?
Ask Councilmember Will Hall. Sidewalks for new developments (i.e., mixed use residential) take priority.
Post a Comment