Aurora Corridor construction update - roadway work
Friday, January 30, 2015
Construction Update
Updated January 26, 2015
Roadway Work
New curb, gutter, and sidewalk construction and irrigation/landscaping work will continue along Aurora between N 200th Street and north of N 205th Street. Concrete driveways will continue to be constructed on Aurora from N 198th Street north, including the side streets. Retaining wall work will continue on N 200th Street. Roadway excavation and grading will continue north of N 205th Street to SR-104. There will be work on the signals and street lighting at N 205th.
During this time, the southbound direction of Aurora and the affected side streets may be restricted to one lane during the daytime non-commute hours to perform any of the work above, weather permitting.
Utility Work
Seattle City Light, Comcast, and Frontier will continue installation of their systems from N 192nd Street to N 200th Street. This work converts the utilities from aerial to underground lines.