Aurora Corridor Construction Update - August 1, 2014
Utility Work
Excavation will continue during daytime hours (7:00am to 3:30pm) for utility work (power, lighting, and communications) on the west side of Aurora.
The contractor plans to install the utility crossings between N 195th and N 200th during the first two weeks of August. During this work, Aurora will be one lane in each direction, generally between the hours of 7:00pm and 5:00am.
The crews will do everything they can to minimize the noise at night; however, night work may present a noise impact to nearby residents and businesses.
Roadway Work
Storm drain work, resulting in trenching and installation of new manholes or inlets, and the construction of new curbs, gutters, and sidewalks is in progress. Southbound Aurora may be restricted to one lane during the daytime non-commute hours to perform any of the work above.
2014 Activities
Activities on the west side of Aurora that will continue through most of this year include asphalt pavement removal, excavation, utility work, curbs, gutters, sidewalks, retaining walls, and paving.
Questions or concerns about construction?
- Call 206-801-2485 - 24 hours a day or email.
Sign up to receive alerts and construction updates on Alert Shoreline
Remember that all the businesses are open. Look for the Business Access signs for the driveways.
No comments:
Post a Comment
We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.