Pages

Monday, August 26, 2013

Shorecrest is scheduled for completion in February 2014

New Shorecrest building
Photo courtesy Shoreline Schools

Drivers on 25th NE may not even realize that a new school is being built on the Shorecrest site. The new building is behind the current building, which will continue in use until the new building is ready for occupancy.

Shorecrest work continues on the main academic building, which is expected to be completed in February 2014. Here's the construction update:

GYM:
  • Grind/polish of locker rooms and associated offices to be completed
MAIN
  • Installation of casework under way. 
  • Installation of gypsum wallboard at all levels to finish
  • Interior painting to be nearly complete
  • Mechanical, Plumbing, Electrical and Fire Sprinkler rough-in continues on all floor levels
  • Window installation to be completed
  • Exterior siding installation continues
SITE
  • Grading and installation of sub-base for parking and drive on northwest side of Area 2 to finish
  • Trenching and installation of main electrical conduit for main power loop around site to finish
  • Installation of waterline for domestic and fire system to begin
  • Installation of sub-grade pipes for building downspouts to begin
  • Installation of sidewalks around the building to continue

Here is a video slide show update on the Shorecrest project:


No comments:

Post a Comment

We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.