Shorecrest is scheduled for completion in February 2014
Monday, August 26, 2013
New Shorecrest building Photo courtesy Shoreline Schools |
Drivers on 25th NE may not even realize that a new school is being built on the Shorecrest site. The new building is behind the current building, which will continue in use until the new building is ready for occupancy.
Shorecrest work continues on the main academic building, which is expected to be completed in February 2014. Here's the construction update:
GYM:
- Grind/polish of locker rooms and associated offices to be completed
- Installation of casework under way.
- Installation of gypsum wallboard at all levels to finish
- Interior painting to be nearly complete
- Mechanical, Plumbing, Electrical and Fire Sprinkler rough-in continues on all floor levels
- Window installation to be completed
- Exterior siding installation continues
- Grading and installation of sub-base for parking and drive on northwest side of Area 2 to finish
- Trenching and installation of main electrical conduit for main power loop around site to finish
- Installation of waterline for domestic and fire system to begin
- Installation of sub-grade pipes for building downspouts to begin
- Installation of sidewalks around the building to continue
Here is a video slide show update on the Shorecrest project: