New Shorecrest anticipated for completion February 2014
Tuesday, July 2, 2013
Shorecrest main academic building and commons |
SHORECREST
The main academic building is on schedule for its anticipated completion in February 2014.
Main Academic Building
West Wing:
- Installation of gypsum wallboard continues on all floor levels, including taping and prep
- Mechanical, Plumbing, Electrical and Fire Sprinkler rough-in continues on all floor levels
- HVAC ductwork installation continues on all levels
- Painting of classrooms to continue on second and third floor levels
Middle Wing:
- Installation of metal stud framing continues on the main floor level
- Mechanical, Plumbing, Electrical and Fire Sprinkler rough-in continues on all floor levels
- Fire proofing of steel structure to complete
East Wing:
- Interior metal stud wall partition framing to continue on all levels.
- Main floor slab on grade to be completed.
- Roofing to continue.
- Fire proofing of steel structure to be completed
Looking north at the Shorecrest academic building |
SITE
Installation of retaining wall along east side of building to continue
Excavation for main electrical vault to begin
GYM
Final punch list items (additional painting, etc.) to be completed over summer break.
THEATER
Final punch list items (additional painting, etc.) to be completed over summer break.
0 comments:
Post a Comment