New Shorecrest anticipated for completion February 2014

Tuesday, July 2, 2013

Shorecrest main academic building and commons


SHORECREST

The main academic building is on schedule for its anticipated completion in February 2014. 

Main Academic Building

West Wing:

  • Installation of gypsum wallboard continues on all floor levels, including taping and prep
  • Mechanical, Plumbing, Electrical and Fire Sprinkler rough-in continues on all floor levels
  • HVAC ductwork installation continues on all levels
  • Painting of classrooms to continue on second and third floor levels

Middle Wing:

  • Installation of metal stud framing continues on the main floor level
  • Mechanical, Plumbing, Electrical and Fire Sprinkler rough-in continues on all floor levels
  • Fire proofing of steel structure to complete

East Wing:

  • Interior metal stud wall partition framing to continue on all levels. 
  • Main floor slab on grade to be completed.
  • Roofing to continue.
  • Fire proofing of steel structure to be completed

Looking north at the Shorecrest academic building
SITE

Installation of retaining wall along east side of building to continue
Excavation for main electrical vault to begin

GYM

Final punch list items (additional painting, etc.) to be completed over summer break.

THEATER

Final punch list items (additional painting, etc.) to be completed over summer break.


0 comments:

Post a Comment

We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.

ShorelineAreaNews.com
Facebook: Shoreline Area News
Twitter: @ShorelineArea
Daily Email edition (don't forget to respond to the Follow.it email)

  © Blogger template The Professional Template II by Ourblogtemplates.com 2009

Back to TOP