Shorecrest construction update
Saturday, May 18, 2013
Looking to the southeast at the new main academic building at Shorecrest. Photo courtesy Shoreline Schools |
SHORECREST - construction update
GYM
Final punch list items (additional painting, etc.) to be completed over summer break.
THEATER
Final punch list items (additional painting, etc.) to be completed over summer break.
View of the north exterior walls of the new main academic building at Shorecrest. Photo courtesy Shoreline Schools |
MAIN ACADEMIC BUILDING
The building is expected to be completed in February 2014.
West Wing:
- Installation is under way of interior metal stud wall framing on first floor.
- Exterior masonry veneer installation continues along south wall; veneer installation to begin along north wall.
- Mechanical and Electrical rough-in to continue at first floor.
- Window installation to continue at second and third floor levels.
- Installation of insulation to continue at exterior walls at second and third floor levels.
- Commence installation of gypsum wallboard at interior walls at second and third floor levels.
Middle Wing:
- Electrical and plumbing rough-in continues at all levels.
- HVAC ductwork installation to continue at second and third floor areas.
- Interior steel stud wall framing continues at all levels.
- Underground electrical installation to commence.
- Concrete floor slab pours scheduled for second and third floor areas at north end.
East Wing:
- Preparation of sub-grade material at main floor level for slab pour to continue.
- Exterior metal stud wall framing to commence at third floor level.
- HVAC ductwork installation to begin.
- Concrete floor slab pours scheduled for second and third floor areas.
SITE
Completion of underground utilities and excavations for site concrete walls continues.
0 comments:
Post a Comment