High School construction update: Shorewood

Friday, May 17, 2013

Add captionThe main south courtyard at the new Shorewood,
looking at the library, center, and the entrance to the commons, right.



SHOREWOOD: 

The entire building remains on schedule to open for the beginning of school in September. 

Electrical rough-in will be completed in Ronald School and sheetrock will be installed this month.

Exterior metal panels installation is nearing completion with the theater being the final area to complete.

Windows at the library, commons, main entry and south classroom entry are nearly complete.

All basketball hoops, divider curtain, speakers, light fixtures have been installed in the gym. Gym floor installation will begin soon.

Casework installation is nearing completion in the classroom building.

Most of the ceiling grid is installed in the building.

The steps leading to the entrance of the new Shorewood.

Main electrical room has been energized with permanent power. 

Light fixtures are installed in most of the classroom building. 

Restroom fixtures, flooring and wall tile installation is complete in classroom building.

Main kitchen equipment is delivered and being installed.

Site concrete continues to be poured with good weather. Main south courtyard is 90 percent complete and north main entry courtyard is 50 percent complete.

Carpet and rubber flooring installation is underway on all three levels of the classroom building

Installation of Culinary arts kitchen equipment is nearly complete.


0 comments:

Post a Comment

We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.

ShorelineAreaNews.com
Facebook: Shoreline Area News
Twitter: @ShorelineArea
Daily Email edition (don't forget to respond to the Follow.it email)

  © Blogger template The Professional Template II by Ourblogtemplates.com 2009

Back to TOP