New traffic signal activated at 61st Avenue NE and NE 181st Street
Tuesday, April 9, 2013
A new traffic signal at the intersection of 61st Avenue NE and NE 181st Street in Kenmore is now in operation and all lanes are open. This safety improvement project included the traffic signal, roadway widening, illumination and placing utilities underground.
A second project was completed in this intersection during this timeframe. Culverts carrying a stream along 61st Avenue NE and underneath NE 181st Street had to be replaced. The new culvert provides additional conveyance capacity, removes fish barriers, and improves fish habitat.
Construction of these improvements began in August 2012. The projects were constructed by Razz Construction out of Bellingham, Washington. The traffic signal was partially funded by a $650,000 appropriation from the State Legislature.