The construction of the new Shorewood High School remains on schedule for the new buildings to open in September 2013.
Elevator installation at both elevator locations is on-going
Looking into the front entrance to the new Shorewood High School, with the Ronald building at left. |
Exterior metal panels installation continues around both the theater, classroom and athletic areas
Windows at the library, commons, main entry and south classroom entry are 95 percent complete
The gymnasium building. |
Painting of the gym ceilings is under way. Ceiling grid installation continues in all areas of the building
Following completion of the gym ceiling painting, athletic equipment will be installed followed by the wood floors
Looking from the courtyard back toward the library and commons area of the new Shorewood. |
Casework and corridor panels are being installed on all levels of the classroom building and nearing completion
Main electrical room has been energized with permanent power to the building.
Restroom flooring, fixtures and wall tile installation is ongoing.
Looking south - Work continues on the courtyard |
Roofing is nearly complete
Site concrete continues to be poured with good weather.