All photos courtesy Shoreline Schools
The concrete slabs for the three classroom wings have been poured.
The concrete masonry wall construction is now 90 percent complete for the gymnasium and auxiliary gymnasium.
The masonry is approximately 50 percent done at the theater area.
In this aerial view, Fremont runs along the bottom of the photo, with Aurora just out of sight along the top. N 175 runs top to bottom along the left of the photo.
The original site design This is for orientation purposes only |
The contractors and design team members are vacating Ronald School soon to allow for interior remodel to begin.
Steel is being delivered, and erection of the three-story building will begin soon.
The project remains on schedule for opening of the new Shorewood in the fall of 2013.
Shorewood High School, 17300 Fremont Ave N, Shoreline 98133
No comments:
Post a Comment
We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.