Aurora construction update for the week of February 12, 2012

Saturday, February 11, 2012

City of Shoreline Aurora Corridor Project
Construction update for the week of February 12, 2012

N 165th - N 185th Streets (Marshbank Construction)

This week, crews will:
  • Continue electrical work on traffic signals and street luminaires.

N 185th - N 192nd Streets (Johansen Excavating)

This week, crews will:
  • Continue installation of concrete curbs and sidewalks.
  • Continue to coordinate with Seattle City Light, Comcast, and Frontier to convert properties from overhead power and communication systems to new underground systems.
  • Continue traffic signal work near the intersection of Aurora and N 192nd Street.
  • Install irrigation lines and topsoil in preparation for landscape installation. Intermittent lane closures on Aurora will be required while large trucks unload.

Puget Sound Energy (PSE) will work at night beginning February 12 to relocate a gas main on Aurora. PSE will work Sunday night through Friday morning between the hours of 7 p.m. and 5 a.m. Gas work is expected to continue for approximately 10 working nights.

Check the website for detailed construction information.



0 comments:

Post a Comment

We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.

ShorelineAreaNews.com
Facebook: Shoreline Area News
Twitter: @ShorelineArea
Daily Email edition (don't forget to respond to the Follow.it email)

  © Blogger template The Professional Template II by Ourblogtemplates.com 2009

Back to TOP