N 165th - N 185th Streets (Marshbank Construction)
This week, crews will:
- Continue electrical work at traffic signals and street luminaires.
N 185th - N 192nd Streets (Johansen Excavating)
This week, crews will:
- Continue installation of concrete curbs and sidewalks throughout the project area.
- Continue to coordinate with Seattle City Light, Comcast, and Frontier to convert properties along the corridor from overhead power and communication systems to new underground systems.
- Continue electrical work near the intersection of Aurora and N 192nd Street to install street luminaires, traffic signal poles, and underground traffic detection loops.
- Install irrigation lines, topsoil, and root boxes in preparation for landscape installation. (Shrubs and trees will be installed once the weather and ground temperature are appropriate for planting.)
Check website for detailed construction information.
No comments:
Post a Comment
We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.