Aurora construction update for the week of January 15, 2012
Sunday, January 15, 2012
City of Shoreline Aurora Corridor Project
Construction update for the week of January 15, 2012
N 165th - N 185th Streets (Marshbank Construction)
This week, crews will:
- Continue landscaping, electrical work (at traffic signals and street luminaires), and property restoration work.
N 185th - N 192nd Streets (Johansen Excavating)
This week, crews will:
- Continue installation of new concrete features, including sidewalks and curbs, throughout the project area.
- Continue to coordinate with Seattle City Light, Comcast, and Frontier to convert properties along the corridor from overhead power and communication systems to new underground systems.
- Continue traffic signal work at the intersection of Aurora and N 192nd Street to install signal poles and underground traffic detection loops.
- Begin preparing for landscaping by installing irrigation lines and root boxes for trees and vegetation.
Base paving on Aurora from N 185th - N 192nd Streets has been completed! Final paving will be scheduled in the spring when the weather is warmer and more predictable.
Check website for detailed construction information.