Aurora construction update for the week of January 10, 2012
Sunday, January 8, 2012
N 165th - N 185th Streets (Marshbank Construction)
This week, crews will:
- Continue landscaping, electrical work (at traffic signals and street luminaires), and property restoration work.
N 185th - N 192nd Streets (Johansen Excavating)
This week, crews will:
- Continue installation of new sidewalks on the east side of Aurora and on N 192nd Street east of Aurora.
- Complete installation of concrete medians and construction of left- and U-turn pockets in the center of Aurora.
- Pave the center lanes of Aurora and the back of business driveways on the east side of Aurora (weather permitting). Driveways will be closed approximately four hours while asphalt cools and cures.
- Begin electrical work at the intersection of Aurora and N 192nd Street to install traffic signal poles and underground traffic detection loops.
Check the website for detailed construction information.