Burke-Gilman Trail construction update

Thursday, December 15, 2011

Burke Gilman Trail
Photo courtesy King County Parks

What's happening on the BGT?
  • The northern segment from Ballinger Way Northeast to Logboom Park will re-open by Dec. 31.
  • The southern segment from Northeast 145th Street to Ballinger Way Northeast is expected to remain closed until late January.
  • The detour will remain in place from Ballinger Way Northeast to 94th Street until the project is complete.

Contractor crews encountered unanticipated issues associated with 100 years of tight development along the corridor, including poor soil quality, drainage and the numerous utility crossings. These problems required extensive redesign and caused delays. Contractor crews have been working extended hours since September to complete construction as quickly as possible. Read the most recent Construction Mailer (12/06/2011).

What's next?

Most remaining work is focused on completing the southern segment from Northeast 145th Street to Ballinger Way Northeast and includes paving and installing safety features, such as fencing, bollards, and intersection treatments. Check back often, as we will continue to provide construction updates on a weekly basis.

Resources for keeping up-to-date on the project



0 comments:

Post a Comment

We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.

ShorelineAreaNews.com
Facebook: Shoreline Area News
Twitter: @ShorelineArea
Daily Email edition (don't forget to respond to the Follow.it email)

  © Blogger template The Professional Template II by Ourblogtemplates.com 2009

Back to TOP