Aurora construction update for the week of November 20 and 27, 2011

Sunday, November 20, 2011

Two week schedule: weeks of November 20 and November 27, 2011

N 165th - N 185th Streets (Marshbank Construction)

Over the next two weeks, crews will:
  • Continue removing temporary signal poles and equipment between N 170th and N 180th Streets.
  • Continue restoration activities along Aurora including landscaping and installation of concrete features. Intermittent lane closures may be required. Restoration work will continue throughout the fall.


N 185th - N 192nd Streets (Johansen Excavating)
  • Over the next two weeks, crews will:
  • Temporarily close access to N 192nd Street east of Aurora for paving work (weather permitting).
  • Pave the work zone and driveways on the east side of Aurora between N 185th and N 192nd Streets (weather permitting); work will require single northbound lane closures.
  • Begin lane striping and center median work, and may shift traffic to the outside lanes of Aurora.
  • Continue street luminaire and pedestrian railing installation.
  • Continue pouring the concrete face of the new retaining wall in front of Sky Nursery.
  • Continue pouring and staining concrete features at the Rain Garden Plaza in the northeast corner of the Shoreline Park and Ride.


Check the website for detailed construction information.

There will be no construction over the Thanksgiving weekend.


0 comments:

Post a Comment

We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.

ShorelineAreaNews.com
Facebook: Shoreline Area News
Twitter: @ShorelineArea
Daily Email edition (don't forget to respond to the Follow.it email)

  © Blogger template The Professional Template II by Ourblogtemplates.com 2009

Back to TOP