Aurora construction update for the week of November 14, 2011

Monday, November 14, 2011

N 165th - N 185th Streets (Marshbank Construction)

This week, crews will:

  • Continue working through the punchlist (final to-do list) including adjusting traffic signs, installing irrigation lines, landscaping, replacing concrete features (such as curb ramps, sidewalks, and driveways), and continuing property restoration. Some work is weather dependant. Work will continue through the fall.

N 185th - N 192nd Streets (Johansen Excavating)

This week, crews will:

  • Pave the work zone at night (Wednesday and Thursday) along the east side of Aurora and on N 192nd Street east of Aurora. Please note days may shift depending on weather.
  • Intermittently close access to N 192nd Street east of Aurora between 9 a.m. and 3 p.m. to grade and prepare the roadway for paving.
  • Continue installing permanent street luminaires along the corridor.
  • Continue pouring concrete on the face of the new retaining wall in front of Sky Nursery and at the Rain Garden Plaza in the northeast corner of the Shoreline Park & Ride. Concrete work will continue for the next several weeks.

Check the website for detailed construction information.

0 comments:

Post a Comment

We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.

ShorelineAreaNews.com
Facebook: Shoreline Area News
Twitter: @ShorelineArea
Daily Email edition (don't forget to respond to the Follow.it email)

  © Blogger template The Professional Template II by Ourblogtemplates.com 2009

Back to TOP