Aurora construction update for the week of October 30, 2011
Monday, October 31, 2011
N 192nd, looking toward Aurora Photo by Diane Hettrick |
N 165th - N 185th Streets (Marshbank Construction)
This week, crews will:
- Continue removing temporary signal poles and equipment between N 170th and N 180th Streets.
- Continue restoration activities along Aurora including landscaping and installation of remaining concrete features. Intermittent lane closures may be required. Restoration work will continue throughout the fall.
- Activate the permanent traffic signal at N 185th Street and Midvale Avenue.
N 185th - N 192nd Streets (Johansen Excavating)
This week, crews will:
- Continue installing curbs on the east side of Aurora and N 192nd Street.
- Remove temporary fencing adjacent to the Shoreline Park & Ride and install a permanent railing. A single lane in the southbound direction will be closed during this work. Periodic sidewalk closures and pedestrian detours will also be required. Please look for designated pedestrian pathways and follow the directions of signs and flaggers.
- Conduct electrical work in preparation for installation of permanent street lighting.
- Continue pouring the concrete face of the new retaining wall in front of Sky Nursery.
- Continue pouring concrete features of the Rain Garden Plaza at the northeast corner of the Shoreline Park and Ride.
Check the website for detailed construction information.
0 comments:
Post a Comment