Updates on the two Aurora construction projects
Sunday, July 10, 2011
N 165th - N 185th Streets (Marshbank Construction)
This week, crews will:
- Continue nighttime installation of underground traffic detection systems for signals. Traffic will be reduced to one lane north and southbound on Aurora.
- Grind and level base paving on Aurora, N 175th Street, and N 185th Street at night in preparation for final paving. Expect lane closures on Aurora, N 175th Street and N 185th Street and higher noise volumes.
- Continue forming and pouring pedestrian islands on N 185th Street west of Aurora. Traffic will be reduced to one lane westbound on N 185th Street.
- Form and pour curbs and sidewalks at the intersection of N 185th Street and Midvale Avenue.
- Form and pour medians on N 175th Street east and west of Aurora. Traffic will be reduced to one lane westbound on N 175th Street. Crews will work during the day all week and at night on Wednesday.
- Continue converting electrical, phone and communications services to new underground systems and removing old overhead lines.
- Continue landscaping along Aurora. A single north and southbound lane on Aurora may be intermittently closed.
N 185th - N 192nd Streets (Johansen Excavating)
This week, crews will:
- Continue controlling the intersection of Aurora and N 192nd Street with uniformed police officers as needed. Officers may at times prohibit left turns onto N 192nd Street due to significant backups on Aurora or for safety concerns.
- Continue installing the joint utility trench on N 192nd Street east of Aurora. Traffic will be reduced to a single lane. Police officers and flaggers will assist with traffic control.
- Complete grading activities on Aurora adjacent to the Shoreline Park & Ride and begin pouring concrete curbs and bus pads.
- Continue excavating the western slope (north of Maaco Auto Body) and existing asphalt in the work zone on the west side of Aurora north of N 192nd Street.
- Begin installing underground communication services following asphalt removal and roadway excavation. Temporary crushed rock driveways will be installed to maintain access to businesses.
- Continue retaining wall construction activities on the west side of Aurora near the Department of Licensing.
0 comments: