Updates on the two Aurora construction projects

Sunday, July 10, 2011

N 165th - N 185th Streets (Marshbank Construction)

This week, crews will:
  • Continue nighttime installation of underground traffic detection systems for signals. Traffic will be reduced to one lane north and southbound on Aurora.
  • Grind and level base paving on Aurora, N 175th Street, and N 185th Street at night in preparation for final paving. Expect lane closures on Aurora, N 175th Street and N 185th Street and higher noise volumes.
  • Continue forming and pouring pedestrian islands on N 185th Street west of Aurora. Traffic will be reduced to one lane westbound on N 185th Street.
  • Form and pour curbs and sidewalks at the intersection of N 185th Street and Midvale Avenue.
  • Form and pour medians on N 175th Street east and west of Aurora. Traffic will be reduced to one lane westbound on N 175th Street. Crews will work during the day all week and at night on Wednesday.
  • Continue converting electrical, phone and communications services to new underground systems and removing old overhead lines.
  • Continue landscaping along Aurora. A single north and southbound lane on Aurora may be intermittently closed.


N 185th - N 192nd Streets (Johansen Excavating)

This week, crews will:
  • Continue controlling the intersection of Aurora and N 192nd Street with uniformed police officers as needed. Officers may at times prohibit left turns onto N 192nd Street due to significant backups on Aurora or for safety concerns.
  • Continue installing the joint utility trench on N 192nd Street east of Aurora. Traffic will be reduced to a single lane. Police officers and flaggers will assist with traffic control.
  • Complete grading activities on Aurora adjacent to the Shoreline Park & Ride and begin pouring concrete curbs and bus pads.
  • Continue excavating the western slope (north of Maaco Auto Body) and existing asphalt in the work zone on the west side of Aurora north of N 192nd Street.
  • Begin installing underground communication services following asphalt removal and roadway excavation. Temporary crushed rock driveways will be installed to maintain access to businesses.
  • Continue retaining wall construction activities on the west side of Aurora near the Department of Licensing.



0 comments:

Post a Comment

We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.

ShorelineAreaNews.com
Facebook: Shoreline Area News
Twitter: @ShorelineArea
Daily Email edition (don't forget to respond to the Follow.it email)

  © Blogger template The Professional Template II by Ourblogtemplates.com 2009