Public Health Laboratories addition is under construction in Shoreline
Sunday, April 10, 2011
Public Health Labs in Shoreline. Photo by Steven H. Robinson |
By Donn Moyer, Communications Office, Washington Dept of Health
Our State Public Health Laboratories facility is building a 10,800 square foot addition at our site on the Fircrest campus on 15th NE in Shoreline.
Construction began last summer. Photo by Steven H. Robinson |
Construction of a new wing at the existing site will include
- secure facilities for storage of laboratory chemicals,
- an approximately 3,400 square foot lab used for the diagnosis and identification of specimens,
- an approximately 2,400 square foot receiving area that will allow the lab to safely receive environmental and clinical samples,
- an approximately 3,900 square foot Mechanical Penthouse,
- and an 1,125 square foot basement.
Exterior roughed in and weatherproofed for the winter Photo courtesy State Dept of Health |
The project was in design phase through the 2007-2009 biennium and is in construction through the 2009-2011 biennium. Completion is projected by June 2011, with occupancy scheduled by September, 2011.
- The addition is increasing existing laboratory and receiving space and is under construction now.
- The groundbreaking was in March 2010 (see story) and construction is expected to end in June 2011.
- Construction progress is on schedule. The contractor is currently working on the interior of the addition; wiring, plumbing, interior walls, and HVAC equipment are being finished.
- The exterior of the building has been roughed-in and is weather-proof so construction has continued through the winter months.
- The addition should be in operation and occupied no later than September, 2011.