City of Shoreline Aurora Corridor Project
Construction update for the week of May 16, 2010
This week crews will:
* Pour curbs and continue grading the roadway on the east side of Aurora between N 165th and N 175th St.
* Install underground components of rain gardens on the east side of Aurora.
* Install vaults and trench for the joint utility trench on Midvale Avenue, N 175th St, N 182nd St, N 185th St and Aurora.
* Continue water line and storm drain work on Aurora between N 165th and N 185th Streets.
* Continue temporarily closing some lanes on Aurora and nearby streets for work activities (some day- and some night-time closures).
Lane closures:
* Monday, May 17 to the morning of Friday, May 21
- Temporary lane closures on Aurora nightly between N 175th to 185th Streets nightly from 8 pm to 5 am.
* Tuesday, May 18 to the morning of Friday, May 21
- Temporary right lane closures on southbound Aurora nightly between 165th to 175th Streets nightly from 8 pm to 5 am.
* Monday, May 17 to Friday, May 21
- Up to one lane on N 175th St, east of Aurora will intermittently close daily from 7 am to 5 pm.
- Up to one lane on Midvale Ave N, east of Aurora will close daily from 7 am to 5 pm.
- Temporary full closures of N 182nd St between Midvale Ave N and Aurora daily from 7 am to 5 pm.
Photo by Steven H. Robinson