Aurora Corridor project May 16 - 21

Friday, May 14, 2010


City of Shoreline Aurora Corridor Project
Construction update for the week of May 16, 2010

This week crews will:

* Pour curbs and continue grading the roadway on the east side of Aurora between N 165th and N 175th St.

* Install underground components of rain gardens on the east side of Aurora.

* Install vaults and trench for the joint utility trench on Midvale Avenue, N 175th St, N 182nd St, N 185th St and Aurora.

* Continue water line and storm drain work on Aurora between N 165th and N 185th Streets.

* Continue temporarily closing some lanes on Aurora and nearby streets for work activities (some day- and some night-time closures).

Lane closures:

* Monday, May 17 to the morning of Friday, May 21
  • Temporary lane closures on Aurora nightly between N 175th to 185th Streets nightly from 8 pm to 5 am.
* Tuesday, May 18 to the morning of Friday, May 21
  • Temporary right lane closures on southbound Aurora nightly between 165th to 175th Streets nightly from 8 pm to 5 am.
* Monday, May 17 to Friday, May 21
  • Up to one lane on N 175th St, east of Aurora will intermittently close daily from 7 am to 5 pm.
  • Up to one lane on Midvale Ave N, east of Aurora will close daily from 7 am to 5 pm.
  • Temporary full closures of N 182nd St between Midvale Ave N and Aurora daily from 7 am to 5 pm.

Photo by Steven H. Robinson



0 comments:

Post a Comment

We encourage the thoughtful sharing of information and ideas. We expect comments to be civil and respectful, with no personal attacks or offensive language. We reserve the right to delete any comment.

ShorelineAreaNews.com
Facebook: Shoreline Area News
Twitter: @ShorelineArea
Daily Email edition (don't forget to respond to the Follow.it email)

  © Blogger template The Professional Template II by Ourblogtemplates.com 2009

Back to TOP